summary bar label

1 reply [Last post]
Jason LI
User offline. Last seen 4 years 13 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

All,

I'm organizing the layout using activity code, all the activity names are using English, and at the right side of the bar, I'm showing the bar label use another language to translate the activity names, so the people didn't know English can read the schedule.

My Question is: are there any way to showing the same for the summary bar (the summary bar label only can show the description of the activity code, but i don't want the activity code description be bilingual)

Thanks for your reply.



 

Replies

Zoltan Palffy
User offline. Last seen 26 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

in the group and sort function uncheck activity name and description and check id/ code