Saving Different Language in P6

R
Ron Liu 👤 Member for 9 years 5 months

Hello everyone,

I have problem saving P6 acitivities that are entered in a different language. I'm using P6 16.1 and my activity description is in Japanese. When I'm done entering the activities and exist the schedule, all activities would display question marks when I open the schedule again.

Does anyone know a fix?

Thank you.

M
Mike Testro 👤 Member for 20 years 7 months

Hi Ron

This may work in P6 but in Asta I set up a user field then copy paste all the English titles into Google Translate and then copy paste the language back. It is not always accurate but it is quick and simple.

The problem with Japanes is that there are 3 different texts to the language so the pictoral versions - Katakana & Hiragana may not work. The letter version Kanji may do better.

Good luck

Best regards

Mike Testro

Featured Partner

Top Posters

Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts
Manjeet Yadav
0 posts
Pan
0 posts
Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts