Many thanks for your answer, but that does not solve the problem, because once I change the calendar for Scheduling Relationships Lag, and reschedule the programme, it will move all my activities. For example, if Activity 1 is linked FS to Activity 2 with 24h lag (1 day with the 24 Hours Calendar), so that activity 2 starts 1 day after activity one finishes, if I change the Calendar for Scheduling Relationships Lag to "predecessor calendar", assuming that Activity one has a 5 days 8h calendar, then, when rescheduling, activity 2 will start 3 days after activity one, or 5 days if there is a weekend in the middle.
Any other solution?
BR
Luis
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Wed, 2017-01-04 18:35
Member for
17 years 4 monthsLuis,As you are using days to
Luis,
As you are using days to measure the duration, provide the lag as 1 day instead of 24 hrs. This may solve the problem.
Best Regards
Kannan
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
8 years 9 monthsThanks Zoltan.
Thanks Zoltan.
Member for
16 years 3 monthsof course it will move your
of course it will move your activities thats the whole point. Your only option then is to adjust each activity duration and lag if any. Good luck
Member for
8 years 9 monthsHi Zoltan,Many thanks for
Hi Zoltan,
Many thanks for your answer, but that does not solve the problem, because once I change the calendar for Scheduling Relationships Lag, and reschedule the programme, it will move all my activities. For example, if Activity 1 is linked FS to Activity 2 with 24h lag (1 day with the 24 Hours Calendar), so that activity 2 starts 1 day after activity one finishes, if I change the Calendar for Scheduling Relationships Lag to "predecessor calendar", assuming that Activity one has a 5 days 8h calendar, then, when rescheduling, activity 2 will start 3 days after activity one, or 5 days if there is a weekend in the middle.
Any other solution?
BR
Luis
Member for
16 years 3 monthsunder scheduel thne options
under scheduel thne options you have the choice a sto which calendar that you want to use for scheduelig relationships.
you can choose the successors calendar, the predecessors calendar, 24 hour calendar, or the Project Default Calendar.
So go to schedule then options then at the bottom choose predecesor calendar