Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Is it possible to set up automatically generated reports

No replies
Shaun Chew
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 4 Dec 2015
Posts: 5
Groups: None

Hello,

I have created a few reports that i need to generate weekly at certain times ( after the weeks schedule has finalised and also at the end of a week when all schedule updates have been entered ). These also need to be generated at specific times of the day, is this possibble to set up in P6 V.7

Thank you