Disappearing Budget values

5 replies [Last post]
John Revere
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 30 Jun 2014
Posts: 13
Groups: None

The resource calendars are a mess and Im wondering if this is an issue as when an actual start date is entered to status the actvitiy the resource cost value is erased immediately? any ideas?

Replies

Raymund de Laza
User offline. Last seen 9 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Try to make changes of the "Duration Type"

John Revere
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 30 Jun 2014
Posts: 13
Groups: None
The resources are not disappearing it's the budget when you click on the actual start of an activity.
John Revere
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 30 Jun 2014
Posts: 13
Groups: None
The resource stays it's the budgeted value that changes to zero.
John Revere
User offline. Last seen 7 years 26 weeks ago. Offline
Joined: 30 Jun 2014
Posts: 13
Groups: None
No it's not being reduced by 8. It automatically disappears or changes to zero when you click on start date. I'm thinking when they setup P6 initially they must of clicked on a box to reset the values to zero. They have assigned resources and wonder if again there is a calculation setting that is causing the disappearance.
Jimmy Xie
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 2 Jan 2014
Posts: 18
Groups: None

Dear John

How is your resource "erased"exactly?

Is it erased as 8 times less compare to the original budgeted unit?