Hello colleagues. I was wondering if there is a way to track changes to the critical path of a project during the lifecycle of the project.
In our projects we usually have a Start date ("Coming into Force") and an End Date ("Acceptance"). Inside a trypical plan we have maybe 6-8 key blocks of work (but many hundreds of individual tasks). The blocks of work are usually something like "Survey", "Permits"; "Manufacturing"; "Installation"; "Testing"; "Commissioning"; "Acceptance". Some of the blocks of work overlap but all of the detailed tasks within the blocks are connected through predecessors and successors. So, we can usually see a Critical Path (as determined by MS Project) from start to finish. The actual critical path at any one time may be, for example, "Permits"; "Installation"; "Commissioning"; "Acceptance". While at another point in time the critcal path may be "Survey", "Manufacturing"; "Commissioning"; "Acceptance". So, as the Plan of Work (POW) evolves through the course of the project, the critical path may vary.
Is there a way to automatically compare just the critical paths of one issue of the POW compared to another? In our case, we issue a completely new POW every month and I have not found a way of retaining a previous plan's CP information inside the current version.
If the following chart shows the evolution of the critical path of a Plan of Work (Earlist at the bottom // most recent at the top), is there a way to create this information by comparing the CPs of individual mpp files? The colourd bars would represent the duration of the "blocks" of work making up the CP.
Replies