Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MS Project- Progress Line

2 replies [Last post]
Alan Boulton
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 11 Dec 2018
Posts: 3
Groups: None

Hi

I have an issue with the progress line in MS Project.

I have a summary bar that has all the sub tasks beneath it with 0% complete. The summarry bar also shows 0% complete, but when the progress line is added to the Gnatt chart it shows all the sub tasks correctly, but the summary task is showing as 100% complete.

Any help greatly appreciated. 

6351
ms_project.png

Replies

Alan Boulton
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 11 Dec 2018
Posts: 3
Groups: None

Thank you Tom.

So in summary the system is behaving as designed (doesn't quite seem logical to me given that the percentage complete is showing as zero). Anyway found another "work around" although not strictly right either.

if you enter 1% against any of the sub tasks the progress line on the summary bar shows something closer to what I thought I would get.

Thanks again Alan  

Tom Boyle
User offline. Last seen 11 weeks 5 hours ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

Alan,

Short Answer: this is apparently as-designed behavior in MSP 2016+.  (The same schedule in MSP 2010 would show 0% for the summary task.)  You could hide the issue by hiding the summary tasks with a filter.

By the way: IMO, progress lines have no place in a computer-based process for schedule progress updating.  (An effective update process would make them redundant with the Status Date line anyway.)  Their math has never been quite right, especially for summary tasks, and I believe their flakiness results from Microsoft's attempts to resolve multiple, conflicting user demands for their final appearance.  (I've never used them since the old string-and-pushpin days.) 

Good luck, tom

(Note: You posted an image on PP that will be visible for only a few hours - I saw it before replying.)