Fixed Works and Duration

6 replies [Last post]
mimoune djouallah
User offline. Last seen 5 years 18 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

hi ms project expert.

 

is there any option to assign a fixed amount of works and a duration to activities,

basically I have the amount of work for the activities from the estimation software, and I want the duration to be independant from the resource assignement is that possible in ms project ( something like fixed duration & units in P6).

 

regards

mimoune

ps

I am not trolling here, for some reason the client wants ms project and i have to live with it :(

Replies

mimoune djouallah
User offline. Last seen 5 years 18 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

sorry for not being clear ( as always)

so basically i am using fixed duratin and effort driven is off. the option Updating task status updates resource status  is off.

 

i don't want ms project to change the work value if i change the duration, and i don't want ms project to change the actual work too and the remaining, everything should be independant ?

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

Rafael,

you can't do it in MSP directly (you need Spider for this). For MSP duration would be driven by average productivity of 2 resources.  

Rafael Davila
User offline. Last seen 1 week 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Evgeny,

If resource A installs 100 bricks in one hour and resource B installs 50 do work and effort is the same for each resource?

How do you plan within MSP for different resources working at the same time on the same activity same work hours but each with different productivity?

Regards,

Rafael

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

mimoune,

I am a bit confused. You write:

<<

...something like fixed duration & units in P6...

..i don't want ms project to change the amount of works too,..

>>

 

I am not familiar with P6, but effectively you want Work, Units and Duration to be fixed. Is it correct?

mimoune djouallah
User offline. Last seen 5 years 18 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

Evgeny

thanks, i am already using the fixed duration, but i don't want ms project to change the amount of works too, maybe using a custom field my help ?

Evgeny Z.
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 13 Jan 2008
Posts: 442
Groups: None

mimoune,

not sure 100% that this is what you need, but the straight answer is that you need to use fixed duration task

http://www.slideshare.net/Shelleyb758/ms-project-2010-task-types-best-uses