unfortunately, no; MS Project does not provide such a scheduling report as Primavera where out of sequence, open ended activities a.s.o. would be high-lighted
to easily (?) retrieve out of sequence activities (activity B with a FS link to activity A started before A is being finished), it needs a VBA script, as a filter cannot select an activity because of its predecessor
Considering my Italian background, great suggestions. Will take under advisement.
From what you are saying, MP does not allow or provides a way to provide a list of out of sequence activities like Primavera log does. Is that correct?
But of course one has to assume that all project team members have been properly instructed on the right way to deal with potential schedule improvements:
1. Take the suggestion to the planner (ECP, or engineering change proposal);
2. Have its overall implications analyzed;
3. Implement the work and schedule change (ECO, or engineering change order).
If the team has NOT been properly instructed, then the project manager has been guilty of a grievous omission and should:
1. Shoot himself;
2. Bury himself.
In that order, of course.
Go, England! (Does the weather ever do anything but rain? In Barbados, we'd never allow that during an important cricket match!)
Before executing your procedure perhaps the judge and jury should check that the guilty person was aware that what he was doing was a capital offence rather than a neater way of getting the job done.
Dig a hole two metres deep, two metres long and one metre wide.
Call the person who did the out-of-sequence work without first ensuring with the planner/PM that the OOS work was not going to be a big problem, and then changing the working schedule.
Shoot the person.
Pour quicklime on the body.
Bury the body in the hole.
Explain to them why they should never do out-of-sequence work without first clearing it.
Apologize for not doing #6 before doing #1 through #5.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi James,
unfortunately, no; MS Project does not provide such a scheduling report as Primavera where out of sequence, open ended activities a.s.o. would be high-lighted
to easily (?) retrieve out of sequence activities (activity B with a FS link to activity A started before A is being finished), it needs a VBA script, as a filter cannot select an activity because of its predecessor
Alexandre
Considering my Italian background, great suggestions. Will take under advisement.
From what you are saying, MP does not allow or provides a way to provide a list of out of sequence activities like Primavera log does. Is that correct?
James B.
Hi, Mike!
But of course one has to assume that all project team members have been properly instructed on the right way to deal with potential schedule improvements:
1. Take the suggestion to the planner (ECP, or engineering change proposal);
2. Have its overall implications analyzed;
3. Implement the work and schedule change (ECO, or engineering change order).
If the team has NOT been properly instructed, then the project manager has been guilty of a grievous omission and should:
1. Shoot himself;
2. Bury himself.
In that order, of course.
Go, England! (Does the weather ever do anything but rain? In Barbados, we'd never allow that during an important cricket match!)
Fraternally in project management,
Steve the Bajan
Hi Stephen
Before executing your procedure perhaps the judge and jury should check that the guilty person was aware that what he was doing was a capital offence rather than a neater way of getting the job done.
Does MP stand for Military Police?
Best regards
Mike Testro
Yes, in MSP or in any other software:
Hope that helps.
Fraternally in project management,
Steve the Bajan