Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Out of Sequence correction

5 replies [Last post]
James Braghini
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 10 Sep 2010
Posts: 25
Groups: None

Does anyone have an easy way to correct out of sequence in MP?

Replies

James Braghini
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 10 Sep 2010
Posts: 25
Groups: None

Considering my Italian background, great suggestions. Will take under advisement.

From what you are saying, MP does not allow or provides a way to provide a list of out of sequence activities like Primavera log does. Is that correct?

James B.

 

Stephen Devaux
User offline. Last seen 39 weeks 14 hours ago. Offline
Joined: 23 Mar 2005
Posts: 667

Hi, Mike!

But of course one has to assume that all project team members have been properly instructed on the right way to deal with potential schedule improvements:

1. Take the suggestion to the planner (ECP, or engineering change proposal);

2. Have its overall implications analyzed;

3. Implement the work and schedule change (ECO, or engineering change order).

 

If the team has NOT been properly instructed, then the project manager has been guilty of a grievous omission and should:

1. Shoot himself;

2. Bury himself.

In that order, of course.

 

Go, England! (Does the weather ever do anything but rain? In Barbados, we'd never allow that during an important cricket match!)

Fraternally in project management,

Steve the Bajan

Mike Testro
User offline. Last seen 26 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Stephen

Before executing your procedure perhaps the judge and jury should check that the guilty person was aware that what he was doing was a capital offence rather than a neater way of getting the job done.

Does MP stand for Military Police?

Best regards

Mike Testro

Stephen Devaux
User offline. Last seen 39 weeks 14 hours ago. Offline
Joined: 23 Mar 2005
Posts: 667

Yes, in MSP or in any other software:

  1. Dig a hole two metres deep, two metres long and one metre wide.
  2. Call the person who did the out-of-sequence work without first ensuring with the planner/PM that the OOS work was not going to be a big problem, and then changing the working schedule.
  3. Shoot the person.
  4. Pour quicklime on the body.
  5. Bury the body in the hole.
  6. Explain to them why they should never do out-of-sequence work without first clearing it.
  7. Apologize for not doing #6 before doing #1 through #5.

Hope that helps.

Fraternally in project management,

Steve the Bajan