Microsoft Project unfortunately i need to unfortunately i need to relevel my resources regularly. thanks anyway alex Hi Alex Use a single FS link Hi Alex Use a single FS link between Task A and B. Then set task A ALAP. If you allow the software to level your resources then it will over ride any logic that you have previously set up. That is why it should never be used. Best regards Mike Testro Log in or register to post comments
Hi Alex Use a single FS link Hi Alex Use a single FS link between Task A and B. Then set task A ALAP. If you allow the software to level your resources then it will over ride any logic that you have previously set up. That is why it should never be used. Best regards Mike Testro
unfortunately i need to
unfortunately i need to relevel my resources regularly. thanks anyway
alex
Hi Alex Use a single FS link
Hi Alex
Use a single FS link between Task A and B.
Then set task A ALAP.
If you allow the software to level your resources then it will over ride any logic that you have previously set up.
That is why it should never be used.
Best regards
Mike Testro