sheduling consective tasks with a must start directly after previous task

Member for

14 years 1 month
Permalink

unfortunately i need to relevel my resources regularly. thanks anyway

alex

Member for

19 years 10 months
Permalink

Hi Alex

Use a single FS link between Task A and B.

Then set task A ALAP.

If you allow the software to level your resources then it will over ride any logic that you have previously set up.

That is why it should never be used.

Best regards

Mike Testro