Hi everyone
I have the work to do the control sheet or work plan from a existent program of construction...but that program is a global contract and the activities don’t have a especific value..only contain the activitie, duration and conecctions between activities...the basics...and that is the result of the kind of contract who have a constant variation in the enginner.
Weel, to calculate the percent value of a activitie i used the duration of the activitie dividing the same into the total of the duration of the construction program.
But that method have various problem, but first take a look of the macro estructure of the programm in project.
[URL=http://img101.imageshack.us/i/pdt125das.jpg/][IMG]http://
img101.imageshack.us/img101/7404/pdt125das.jpg[/IMG][/URL]
Uploaded with [URL=http://imageshack.us]ImageShack.us[/URL]
Like can you see, the activities and durations, have a 125 days of total duration, but that not fix into the percent values...cause only one activitie have the total duration of the program having hse only the 100% total ..and the others activities are contain into the days of duration of this activitie...and when i make the sum of the principal percents...they are over the 100%.
Can someone help me in my problem tell me how i can fix it or show me a example to use?
Thanks
Replies