Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project Start Date

6 replies [Last post]
Gerry Cullen
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 4 Nov 2008
Posts: 5
I have inported tasks from an excel spreadsheet to microsoft project. This has set the project start date. I have tasks that are before the date I began to build up the programme. I have added all links to the programme. When I am trying to reset the start date to the actual beginning of the first task it drags all the items linked with it. Can anyone tell how to change the start date but leave all other areas unchanged, e.g. durations, links etc.

In other words I just want to remove the enbedded start date which is when I first started to produce the programme?

Replies

Darren Kosa
User offline. Last seen 7 years 40 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None
Gerry,

I’m a little confused.

The start date signifies the start of the project. The rest of the schedule should be driven by a precedence network. Most, if not all of the activities will have a finish-start relationship, i.e. the next task in the chain will start after the preceding task is complete.

When the first task in your schedule is complete what happens? Does everyone just down tools and hang around or is there something else that happens in the meantime?

If in the unlikely event that nothing else is going to happen, why do you have to start the project on that date?

I can think of a couple of quick workarounds that might help you out, however, from a planning perspective I wouldn’t particularly recommend either of them. It’s just manipulating the scheduling software to show a contrived view of the project.

Option 1
Add soft constraint dates on all the ensuing tasks so they start on the correct dates.

Option 2
Add a lags on all the ensuing tasks so they start on the correct dates.

Regards,

Darren
Mark Chapman
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 18 May 2006
Posts: 183
Groups: None
You don’t need to remove all the links but just the key link.
Gerry Cullen
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 4 Nov 2008
Posts: 5
Is there a way of removing the links and puting them back quickly. The only way I know to put them back is one at a time?
Mark Chapman
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 18 May 2006
Posts: 183
Groups: None
I don’t think I understand but how about temporarily removing the link?
Gerry Cullen
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 4 Nov 2008
Posts: 5
I did try this but because the tasks after the start date are linked when I amended the start date as you suggested all the follow-up tasks also moved.
Stephen Cummings
User offline. Last seen 13 years 13 weeks ago. Offline
Joined: 12 Sep 2007
Posts: 5
Groups: None
Gerry , the following should help

using the top toolbar
project
project information
select your project start date
ok