Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

how to see the predessor and successor form in MSP?

5 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
dear all ,
can anyone advise me as to how the pred/succ form seen in MSP.
regards
deb

Replies

Pranab Kumar Deb
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear Darren,colin and Pinan,
Thank you very much for the tips, this is exactly what i needed , same view of P3.
regards
deb
Darren Kosa
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 8 Feb 2008
Posts: 256
Groups: None
Hi Deb,

Another variation for seeing predecessors / successors in a visual format... as if you need another ;o)

Window > Split > and then click anywhere in the Task Form

Then you need View > More Views > Relationship Diagram

Whenever you select a task in the Task Entry you will also get a graphical representation in the Split Window.

Might be a bit meaningless for most, but it’s helpful for some.

Regards,

Darren
Colin Blair
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 22 Apr 2004
Posts: 29
Groups: None
Hi Pranab

Try Window / Split
Right click on the bottom window - select Predecessors & Successors
This will give you the Task Form

For the Task Details Form -
(make sure you have clicked in a field in the bottom pane)
View / More views
Select Task Details Form
Apply

(Note-You can set up a custom view which will retain this view)

Is this what you’re after

Colin
faisal afsar
User offline. Last seen 12 years 9 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 55
Groups: None
Dear friend

Double click on any task a tab will appear go to predessor and u can see it

Regards

Faisal

PINAN T.
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
In Task Information only, or use Column..