hello ppl
this may be a newbie question, but i cannot seem to solve it...
i am a video editor and i often endeavour in several connected tasks, so i am creating a project to do a proper estimation of times and costs and resource assignments.
i entered the human operators as a work resource, but i really need to enter computers as well and this is where my problems start.
i want to know mainly if their use is overallocated
there are certain tasks where they are useless if not operated by humans, tasks that do require human intervention.
there are other tasks where they can work on their own
they are equipment and i dont know how to set them.
not as a work resource, because when they are driven by humans, assigning the computer and a human resource would split in half the task duration.
certainly not as materials, because their use is not measured in units, and because such a resource cannot be overallocated.
i hope i made myself clear
thank you very much
ps. i use microsoft project 2003
Replies