Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Optimum activity numbers in project for best schedule

1 reply [Last post]
Kutluhan ERGIN
User offline. Last seen 16 years 45 weeks ago. Offline
Joined: 29 Mar 2006
Posts: 6
Groups: None
i m working Engineering Management and Consulting Services and we are consulting iron and steel works companies modernization projects.

we have scheduled all projects with ms project and when i finished schedule of a modernization project. approximately i have 4000 or 5000 activity in my schedule.
i m sure that, too many activities are not focusing the critical path cause of many kind of different works in a project.

i’ve seperated civil construction works, mechanical erection works, bidding and procurement works and electrical-automation works from my first schedule, and i wanna assamble one master schedule from these programs but i cant use the external task or ghost.

anyone have a idea about optimum activity numbers for the best critical path or what is the optimum detail for a project

Replies

Niek Zonneveld
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
What is the average size of your activities?

Don’t forget that you need to update the schedule and recalculate the critical path after the remaining work is rescheduled. This effort can exceed your weekly/monthly update capacity if the activities are very small.

H.T.H.