Hi All,
I was trying to experiment on smaller scale for resource assignments. The steps involved were ,
1) I created a task with different combination of characteristics like fixed duration ( effort driven ) , Fixed duration ( with effort duration off ) , fixed units ( effort driven and effort driven off ) & fixed work.
2) Duration of 44 hrs were assigned to tasks.
3) resouce assigned was 1 unit for each task.
4) in task usage view , last day 4 hours was changed to 16 hours , since on that day two person ( i hoped ) will work.
5) In final stage , i saw for all the tasks , peak resource assignment in graph on last day was showing 6 , contrary to what i expected that max it should be 2 , since two resources would be sufficient to complete 16 hours of work on last day.
IS this behaviour normal ?
Thanks,
with regards,
vinod
Replies