Resource units

2 replies [Last post]
vinod raturi
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 14 Aug 2006
Posts: 57
hi ,

My query is suppose my project calander is 8 of hrs and my resource calander is 24 hrs. If i have to assign that resource to a task that consumes 4 hrs , what should be my assignment fig for that resource , should it be 50% or 16%.

Replies

vinod raturi
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 14 Aug 2006
Posts: 57
hi Zhang ,

I think 16% is correct . My logic being a resource is available to us as per their base calanders , so it is with respect to that time available we should fill in the assignment units.

Any different Views ?
Zhang Haixiang
User offline. Last seen 4 years 16 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
It’s a complex issue.

In MSP there are 3 types of task, fixed duration, fixed work and fixed units. they act differently when assign/change recource.

for your question, use 50%, but maybe the duration will change based on task type.

Goto online help for details for task type,then try it