EV = BCWP = Earned Value has nothing to do with the status date. So in order to get this right you need to build your own spreadsheet in MS Project (with formulas in custom fields) or push the whole lot into Excel; Which is probably the shortest option.
This is probably the Microsoft way of showing that integration between their office products is so seamless :-)
I havent tried working Earned Value with any planning software and very much contented doing it with MS Excel sheets. Earned value has nothing to do with status date, I believe, since the formula alone says BCWP (Earned Value)= % Complete x Budget.
To Planners,
For those not familiar with Earned Value or BCWP (Budgeted of Work Performed), this is very important on tracking project costs and comparing with schedule (BCWS) and actual values (ACWP). I recommend reading the book of Mr. Fleming (Earned Value Management Systems).
I dont know if its common practice to answer to your own thread but here we go anyway.
MS Project takes the baseline start into consideration when it calculates the BCWP (=EV). An activity which was not supposed to have started will not receive any Earned Value, no matter the percentage complete.
Since this is utterly wrong youll need to create your own custom EVM-fields with formulas in MSP, or push the whole lot into Excel.
I hope this saves other people some time (and frustration) in figuring out what the hell is wrong with the EVM numbers from MSP.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
You are right Rommel,
EV = BCWP = Earned Value has nothing to do with the status date. So in order to get this right you need to build your own spreadsheet in MS Project (with formulas in custom fields) or push the whole lot into Excel; Which is probably the shortest option.
This is probably the Microsoft way of showing that integration between their office products is so seamless :-)
Cheers,
Niek.
Just to correct my error that BCWP is Budgeted Cost of Work Performed
To Nick,
I havent tried working Earned Value with any planning software and very much contented doing it with MS Excel sheets. Earned value has nothing to do with status date, I believe, since the formula alone says BCWP (Earned Value)= % Complete x Budget.
To Planners,
For those not familiar with Earned Value or BCWP (Budgeted of Work Performed), this is very important on tracking project costs and comparing with schedule (BCWS) and actual values (ACWP). I recommend reading the book of Mr. Fleming (Earned Value Management Systems).
Regards,
Rommel
Hi Nick,
Although you answer your own question, you have done the best for planners.
I do believe EARNED VALUE is the future for planners.
I encourage you to move on and tell us more about EARNED VALUE.
Cheer,
I dont know if its common practice to answer to your own thread but here we go anyway.
MS Project takes the baseline start into consideration when it calculates the BCWP (=EV). An activity which was not supposed to have started will not receive any Earned Value, no matter the percentage complete.
Since this is utterly wrong youll need to create your own custom EVM-fields with formulas in MSP, or push the whole lot into Excel.
I hope this saves other people some time (and frustration) in figuring out what the hell is wrong with the EVM numbers from MSP.
Cheers,
Niek.