Hi - MSP Help has some info on this which may be of use. I have also used this to explain the differences, which I have shown below - hope this is of use to you.
Fixed Duration:
The task will remain at whatever duration value has been entered provided effort driven is turned off. If two painters assigned full time for 4 days, duration is 4 days. If additional two painters are assigned, then each painter will be assigned for 50% of their time to keep the duration the same.
Fixed Units:
The allocation (i.e. percentage) of a resource drives the resource requirement. For example, if the task is of 4 days duration and two painters are allocated full time (100%), the painters workload total will be 8 days of work. Again, provided effort driven is turned off, if an additional two painters were assigned, then the total workload would be 4 men x 4 days = 16 days of work, but the duration would remain at 4 days. However, if effort driven is turned on, the duration will be recalculated based on the additional resources assigned to 2 days.
Fixed Work:
As resource assignments are changed, MS project will recalculate the duration e.g. if two painters assigned for 4 days, then two more are assigned to the task, the task duration is reduced to 2 days i.e. the total work content of the task remains constant. Effort driven automatically turned on.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Tony
Thanks alot, I see you are in the North West of England, I am originally from Manchester, now living in Toronto, Canada.
Thanks again for the help, Gerry.
Hi Gerry,
Glad that the info was of help.
The information was retrieved from MS Projects own Help guide and not from their web-site (just to save you a bit of time looking!)
I typed "fixed duration" into the search facility, and it then gives you a selection of related help subjects.
Regards,
Tony
Hi Tony
Thanks for taking the time to reply and explain, it was a big help, I will also check out the Site.
Regards Gerry
Hi - MSP Help has some info on this which may be of use. I have also used this to explain the differences, which I have shown below - hope this is of use to you.
Fixed Duration:
The task will remain at whatever duration value has been entered provided effort driven is turned off. If two painters assigned full time for 4 days, duration is 4 days. If additional two painters are assigned, then each painter will be assigned for 50% of their time to keep the duration the same.
Fixed Units:
The allocation (i.e. percentage) of a resource drives the resource requirement. For example, if the task is of 4 days duration and two painters are allocated full time (100%), the painters workload total will be 8 days of work. Again, provided effort driven is turned off, if an additional two painters were assigned, then the total workload would be 4 men x 4 days = 16 days of work, but the duration would remain at 4 days. However, if effort driven is turned on, the duration will be recalculated based on the additional resources assigned to 2 days.
Fixed Work:
As resource assignments are changed, MS project will recalculate the duration e.g. if two painters assigned for 4 days, then two more are assigned to the task, the task duration is reduced to 2 days i.e. the total work content of the task remains constant. Effort driven automatically turned on.