Resource Expenses

2 replies [Last post]
Forum Guest
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
All

Using Project 2003. I have to enter a standard resource cost and then apply a daily per diem cost on top of that for a period of time. Eg:

1-31 Jan - £300/day
1-29 Feb - £300/day + £28/day
1-31 Mar - £300/day

I have to differentiate this £28/day cost as an unbillable expense but still need to be recognised as part of the project cost.

What is the easiest way to do this?

Thanks in advance

Dan

Replies

Forum Guest
User offline. Last seen 8 weeks 1 day ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Thanks

I’ve had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.

If anyone can think of a smarter way of doing it, please let me know.

Dan
Will Russell
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
Using the Cost tab in the Resource Information box you can put in specific costs for certain periods of time as you wanted.

Will