Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

End-of-window (retrospective) validation in TIA with a SRP

No replies
Ollie Lecm
User offline. Last seen 4 years 46 weeks ago. Offline
Joined: 25 Jul 2019
Posts: 10
Groups: None

Hi guys,

I'm working on a project where the contractor issued a schedule recovery plan (SRP) at the end of a certain window. The contractor had impacted Owner's event into the network to determine their EOT entitlement.

My question is: how do we retrospectively validate the impacted results of the window immediately prior to the issuance of SRP when the end-of-window update is the SRP?

Thanks!