Contractor to provide a critical path (as-built versus as-planned) schedule analysis

1 reply [Last post]
Md Manjar Nadeem
User offline. Last seen 2 years 51 weeks ago. Offline
Joined: 9 Feb 2013
Posts: 9
  • Contractor to provide a critical path (as-built versus as-planned) schedule analysis for the Work assigned to Contractor which takes into account concurrent delays and the delays caused by Contractor.

As a contractor we submitted Global Claim at end of project (Civil+MEP) , As per above statement from Client I feel it's confusing they asking Two Schedule Analysis method together , critical path schedule analysis at this end of project is not possible because schedule is already actualised, as-built vs as planned is easy and possible - Any Claim expert could you clarify above statement & my approach is correct??

Replies

Mike Testro
User offline. Last seen 36 weeks 5 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi MD

The text is a clumsy description of a Time Impact Analysis.

Global claims always fail in a tribunal but they can be a useful negotiating tool.

Best regards

Mike Testro