Hi,
The contractor was handed over the land to build the road for the govt. agency. Some utilities need to be shifted in which statutory undertakers (SU) were involved. As per the contract, the contractor needs to pursue the matter with the SU for obtaining the necessary permits even though there was no direct contractual liability for the SU in the agreement between the govt agency and us. Now we are delayed due to the delay in obtaining permission.
What I want to know is:
1) Can the contractor directly address the statutory undertaker. Will such a communication stand legally valid and hold the undertaker responsible?
2) can I claim EOT, even though a part in the contract states that no compensation will be there for delays by authorities.
3) can the employer, in the contract pose such a condition of transferring the responsibilty of obtaining clearance on to the head of the poor contractor?
please HELP
Regards,
K. Satish Kumar
Replies