Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2013-01-28 15:35 Permalink Hi Amar 28 calendar Hi Amar 28 calendar days. Best regards Mike Testro Member for 14 years Member for 14 years Submitted by Ammar Al-Saket on Mon, 2013-01-28 15:23 Permalink Thanks a lot Mike,Just to Thanks a lot Mike, Just to make sure that I've understood you correctly; say I have the following situation: project has 3 activities namely: A,B & C linked Finish-to-Start relationship. activity D is the project completion "finish-milestone". calendar used for all activities is 5 working day calendat Time for Completion of the Works is counted in calendat days An excusable and compensable delay event had delayed the completion date of the project (milestone D) for 4 weeks (20 working days) So, is the compensation for 28 days or for 20 days? Thanks again Ammar Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2013-01-28 11:14 Permalink Hi Ammar Retain the working Hi Ammar Retain the working calendar for the impacted tasks. The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar. The impacted events in the fragnet may have different calendars as required. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2013-01-28 15:35 Permalink Hi Amar 28 calendar Hi Amar 28 calendar days. Best regards Mike Testro
Member for 14 years Member for 14 years Submitted by Ammar Al-Saket on Mon, 2013-01-28 15:23 Permalink Thanks a lot Mike,Just to Thanks a lot Mike, Just to make sure that I've understood you correctly; say I have the following situation: project has 3 activities namely: A,B & C linked Finish-to-Start relationship. activity D is the project completion "finish-milestone". calendar used for all activities is 5 working day calendat Time for Completion of the Works is counted in calendat days An excusable and compensable delay event had delayed the completion date of the project (milestone D) for 4 weeks (20 working days) So, is the compensation for 28 days or for 20 days? Thanks again Ammar
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2013-01-28 11:14 Permalink Hi Ammar Retain the working Hi Ammar Retain the working calendar for the impacted tasks. The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar. The impacted events in the fragnet may have different calendars as required. Best regards Mike Testro
Member for
19 years 10 monthsHi Amar 28 calendar
Hi Amar
28 calendar days.
Best regards
Mike Testro
Member for
14 yearsThanks a lot Mike,Just to
Thanks a lot Mike,
Just to make sure that I've understood you correctly; say I have the following situation:
Thanks again
Ammar
Member for
19 years 10 monthsHi Ammar Retain the working
Hi Ammar
Retain the working calendar for the impacted tasks.
The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.
The impacted events in the fragnet may have different calendars as required.
Best regards
Mike Testro