Calendar to be used for evaluating the impact of delay event

Member for

19 years 10 months

Hi Amar

28 calendar days.

Best regards

Mike Testro

Member for

14 years

Thanks a lot Mike,

Just to make sure that I've understood you correctly; say I have the following situation:

  • project has 3 activities namely: A,B & C linked Finish-to-Start relationship.
  • activity D is the project completion "finish-milestone".
  • calendar used for all activities is 5 working day calendat
  • Time for Completion of the Works is counted in calendat days
  • An excusable and compensable delay event had delayed the completion date of the project (milestone D) for 4 weeks (20 working days) 
  • So, is the compensation for 28 days or for 20 days?

Thanks again

Ammar

Member for

19 years 10 months

Hi Ammar

Retain the working calendar for the impacted tasks.

The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.

The impacted events in the fragnet may have different calendars as required.

Best regards

Mike Testro