Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delay Analysis

6 replies [Last post]
Sunil Babu
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Dear All,

Currently I am working in a DG Sewerage project, our task is to calculate the delay for each shaft.

My question is that how to link the delayed days with the total float of the BL . Also other than window 

analysis is there any other methods of delay analysis which best suited for this project.?

Your comments will be highly appreciated.

Regards,

Sunil.

Replies

Sunil Babu
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Mike,

Thanks a lot for your valuable reply..

Best Regards,

Sunil

Mike Testro
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Sunil

The same principles apply no matter who is operating the rigs.

Best regards

Mike Testro

Sunil Babu
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Mike,

Thanks once again for your valuable reply, another problem in in the change of logic is that

there are defferent contractors operating for these rigs and we have to allocate them accordingly

depends on various conditions..

Best Regards,

Sunil.

Mike Testro
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Sunil

So you have 5 rigs deployed on a number of shafts.

So when rig 1 has finished it moves on to shaft 6 and so on.

You should arrange the shafts into groups of 5 and link Shaft 1 to shaft 6 > shaft 2 to Shaft 7 accordingly.

You can also set up rig resources numbered 1 to 5 and allocate them to the appropriate shafts.

Now if - say - shaft 3 is delayed then rig 3 will be late starting shaft 8 and all of rig 3 allocated shafts will be delayed.

However you must be prepared to rearrange (mitigate) the sequencing so Rig 3 could go to shaft 10 and rig 5 drop onto shaft 8 etc.

This is done by adjusting the logic.

Best regards

Mike Testro

Sunil Babu
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Mike,

Thanks for your reply, actualy this is a deep gravity sewerage project and the programme

was made based on the logic of rig movements, for example five rigs are in operatin under which

the total shafts are diveded into five groups , Various facts affecting the delay such as 

delayed ifc drawings,traffic permits, rig break down, excavation in hard rock etc.

Can you explain further on "knock on effect" based on these factors..

 Regards,

Sunil.

 

Mike Testro
User offline. Last seen 1 day 11 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Sunil

I do not know what a DG Sewage Project is but I am assuming that it is not important.

It is easy to calculate the delay for each shaft by impacting the delay event that caused the delay and then comparing with the actual progress.

Unless there is some logic linking the shafts to the completion date then there will be no "knock on" effect from each standalone shaft to the rest of the programme.

So in order to see the effect of float on the Baseline Programme then some realistic logic has to be in place.

This logic could be physical or resource driven or both.

If you are putting it into an already approved programme you will be accused of rigging it.

Best regards

Mike Testro