Hi all,
I am currently working for a nominated specialist subcontarctor on a building project.
We are preparing to launch a application for EOT.
We have enough evidence to prove that that there has been a delay to the structural work by 4.5 months, reflected in the main contractor latest issued programme.
We thus revised our installation programme based on their latest structural handover date, which has been agreed in principle.
We will be applying for EOT based on the revised programme, which I will defined as our entitlement programme.
Thus I will formally write in to inform the main contractor that we will be apoplying EOT against our subcontract completion date which will be extend from DD/MM/YYY to the completion date as stated in the entitlement programme. The delta is the amount of tiem to be claimed.
Is this a professional way of doing it ? Kindly advice.
If the revised programme is approved, does it automatically relieve myself from the previous contractual obligation. My guess is it will not that why I need to apply for EOT. Am I right in this sense?
Thanks
Replies