Max temperature allowed for labor in construction site ???

6 replies [Last post]
Jehad Aldaoud PMP...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Hello all, I am sorry to start with a question

but i need realy any help, in my problem, 

my problem is there is a project for my company in Jordan - death sea, the our contract with the client is (design-build) contract. we are delay because the designer that work with us he is the cause of our delay, this is summary for the problem .I want to depend in my case in temperature to take extension of time from the client put my problem is I don't have the maximum temperature allowable for labor inconstruction site, can you guide me when I can find this temperature ???

 

Replies

Jehad Aldaoud PMP...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Thank you very much Satish, I sent my problem to Samer

Thank you again  

best regards 

jihad aldaoud 

Jehad Aldaoud PMP...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Thank you very much Satish, I sent my problem to Samer

Thank you again  

best regards 

jihad aldaoud 

Satish Kumar
User offline. Last seen 8 years 2 weeks ago. Offline
Joined: 8 Feb 2010
Posts: 56

 

Hi Jiahd,

 

check for samer in the link below under the heading (highest users)

http://www.planningplanet.com/members

 

Regards,

K

Jehad Aldaoud PMP...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Thank you Mike for your answer, but can you tell me who is Samer ???

Jehad Aldaoud PMP...
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

Thank you Mike for your answer, but can you tell me who is Samer ????

Mike Testro
User offline. Last seen 12 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Jiahd

Welcome to planning planet

When I worked in Baghdad the rule was shade temperature in excess of 50 deg then all work stopped.

The official temperature from the Ministry never exceeded 49.5 deg.

It may be different in Jordan so maybe you can google the question or send a message to Samer.

Don't forget that in Ramadan different rules may apply.

Best regards