Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

can i have a sample of TIME IMPACTED PROGRAM

8 replies [Last post]
Mervilyne Pangan...
User offline. Last seen 24 weeks 4 days ago. Offline
Joined: 25 May 2009
Posts: 53
hi,

i submit an EOT but the client insist to submit us Time impacted program..

tnx,

Replies

Mike Testro
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Mervilene.

I regret that it not possible for me to carry out a delay analysis for you through PP.

Best regards

Mike Testro
Mervilyne Pangan...
User offline. Last seen 24 weeks 4 days ago. Offline
Joined: 25 May 2009
Posts: 53

Hi Sir Mike,

Thanks for the advise, but im a little hesitant because i cannot find the time delay in our side..sir is it ok to give you a copy of the program i made?can i have your email add?

Thanks,
Mike Testro
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Merviliyne

You have demonstrate direct cause and effect of every event individually (causal nexus).

To do this each delay event has to be impacted on the baseline programme in strict chronological order of impact date.

After the impact you review the effect on:

1. The critical path
2. Relationship to youre As Built programme.

You do this in turn for every event.

It is no good just putting some new activities in and rescheduling because you will get a global result.

Also you must put in ALL delay events both client and contrsctor.

Best regards

Mike Testro
Mervilyne Pangan...
User offline. Last seen 24 weeks 4 days ago. Offline
Joined: 25 May 2009
Posts: 53
hi guys,

I made a new program. I used same duration in approved claused 14 program... add some activities..show variance at completion to show the number of days delay...What other important things i need to do to get a claim?

Please advise....


Thanks,
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mervilyne,

Did you read the following report;
http://www.aacei.org/technical/rps/52r-06.pdf

Mike will also provide you with hands on expert advise.

Best Regards,

Samer
Mervilyne Pangan...
User offline. Last seen 24 weeks 4 days ago. Offline
Joined: 25 May 2009
Posts: 53
hi,

tnx guys....

I made a new one but I used my clause 14 as a baseline and add some additional works on it and update with the actual situations on site.

Any suggestions????


Thanks,
Mike Testro
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Mervilene.

A Time Impact programme is usually accepted as the most reliable method of delay analysis.

However it does not work for delays to work in progress where an Impacted as Planned is the only available method.

Please let me know if your analysis is retrospective (forensic) of current work and I can advise you further.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mervilyne,

You can find plenty of information by googling the web. Try to review the following as well:

http://www.slideshare.net/ChrisWCarson/cmaa-prospective-tia

Best Regards,

Samer