Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project not recoverable

7 replies [Last post]
Patrick Homer
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 24 Apr 2008
Posts: 6
Groups: None
I am looking for any papers or books that discuss the probability that a project has a low or no probability to recover time from a series of substantial project delays by the owner and others.

I have a construction job that is greatly behind schedule due to delays by others. The owner wants a recovery schedule to finish the project per original schedule. The owner is willing to pay acceleration costs, but the project is too far behind schedule to recover to the original dates.

Thanks in advance

Replies

Alistair Blakey
User offline. Last seen 10 years 18 weeks ago. Offline
Joined: 20 Feb 2009
Posts: 6
I agree with Neil (post below) regarding risk analysis. The more you squeeze the construction durations and attempt to rationalise the programme by running activities concurrently, the greater your exposure to risk. Eventually you will have a programme which might look possible on paper, but will fall down as soon as one of your (now hypercritical) activities falls behind. Better to inject a note of realism into the project now and try to set a realistic and achievable completion date.
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Partick,

The project duration can be reduced.

The basic idea would be to look at the critical path activities. Then you will select the least expensive activity and start reducing the time by increasing the resources. With each run, you would have reduced the time and increased the cost (acceleration). The critical path will change slowly, and you will need to keep doing the same process until you are satisfied.

With kind regards,

Samer
Patrick Homer
User offline. Last seen 15 years 27 weeks ago. Offline
Joined: 24 Apr 2008
Posts: 6
Groups: None
Thanks all for the responses.

The Owner has granted EOT in the past. I am just presenting the Owner with various options at this time; one of which is that project delay cannot be recovered with acceleration or resequencing this time.
Toby Hunt
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 26 Jul 2007
Posts: 98
Groups: None
Patrick

Try reading Pickavance’s book Delay & Disruption in Construction Contracts, Chapter 11 titled "Mitigation and Acceleration"

Regards

Toby
Neil Tait
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 31 Jan 2001
Posts: 29
Groups: None
Patrick,

In terms of looking at probability of achievement you could look at risk management. There are various papers / background floating about that explain the concept and calculation of risk and its impact upon the programme / schedule and costs. However, in your case it appears that the risk of overrun has already materialised into reality.

If resequencing and assignment of increased resources does not yield an acceptable acceleration / delay recovery programme you need to start thinking out of the box: perhaps the introduction of sectional completion dates will satisfy the client’s needs; perhaps the project is no longer viable and the client needs to cut their losses;...

To enable their decision, the client needs to be presented with the various options in terms of time and cost - the starting point being ’what if we do nothing’ and simply pursue the EOT route. Generally an optimum (sensible) position regarding acceleration / recovery of time and cost can be established. ’Impossible’ and ’backhole’ (where your money will go) are concepts that are generally not too difficult to explain but you do need to present options to give the client a way out.
Mike Testro
User offline. Last seen 35 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Patrick

What Samer says is correct as far as Acceleration is concerned.

But it seems you have grounds for an Extension of Time so why not pursue that Avenue.

If you are going to plan an acceleration conentrate on the tasks that are critical.

Best regards

Mike Testro.
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Patrick,

If you want to consider acceleration, then you need to have an approved schedule, resource loaded. You will keep increasing the resources and reducing the construction time whenever possible. Finally, you will have the minimum duration with which the project can be completed, and the associated cost with the reduction in time (acceleration).

Hope that the information helps.

Best Regards,

Samer