Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Retention & Performance Bonds

5 replies [Last post]
Sajid Balma
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
Dears
Will somebody tell me the difference between Retention & Preformance Bonds? I will be gratefull.

Replies

soumendu ghosh
User offline. Last seen 14 years 28 weeks ago. Offline
Joined: 30 Jul 2003
Posts: 8
Groups: None
Sajid

The release criterea for these bonds are as follows:

Retention Bond - as per contract conditions, for eg, in one of our jobs(FIDIC Contract),the Contractor is required to provide a Retention Bond upon receipt of the Taking Over Certificate for the "whole of the Works" equal to 2.5% (two and a half percent) of the Contract Sum.

Performance Bond - is usually released upon successful completion of the Defects Liability Period.

"Whole of the works" typically denotes that all conditions/services of the Contract have been achieved to the satisfaction of the ’Engineer’

Sajid Balma
User offline. Last seen 13 years 23 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
Further to earlier question, I still wonder if these bonds have time constraints on them. Like one services from prject starts to certain date & other from another date to a different date.
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi,

RETENTION OR RETAINAGE – Usually refers to a percent of contract value retained until work is finished and testing of equipment is satisfactorily completed.

PERFORMANCE BOND – A bond that is executed in connection with a contract and which secures or guarantees the completion, performance and fulfillment of all the work, undertakings, covenants, terms, conditions, and agreements contained in the contract.

Regards,

Arnold
Larry Rino
User offline. Last seen 1 year 29 weeks ago. Offline
Joined: 25 Oct 2007
Posts: 64
SB,

In other thoughts:

Retention bond is same purpose as retention money. However, it is in the same form as Performance bond or Bank guarantee that was issued by Contractor to Client.

Retention bond is in Client possession and was done instead of withholding money from Contractor interim payments.

Cheers
santanu purkayastha
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 8 May 2008
Posts: 11
Retention Money is nothing but the money which is being taken under hold from the ongoing invoices (retention is relate to workmanship) from sub contractor / vendor. e.g. a s/c finished a rcc structure - now if anything happens to that structure any failure,destruction relate to s/c due to his bad workmanship, the same amount will be debited from his (s/c) retention money.

And the Performance Bond or Bank Guarantee is the amount which (performance bond relate to performance) is being given by the s/c or vendor before taking the job LOI e.g. if anything stops/hold the job by the main contractor than the same amount will be debited from that performance Bond.

Thanks

Santanu P.
Gurgaon
98992 98682