Hello,
Just to increase the headache, the client employed a project management consultant to supervise the contractor (our company) and the consultant, this PMC wasnt mentioned neither in the contract conditions (FIDIC 99 1st edition) nor the project specs., hence I assume that we ll issue our claim against this employment near the projects completion (due to their running cost).
Now this PMC requests that we issue a weekly progress report. The specs. dont mention any progress reports rather than the monthly progress report.
The problem is that the contents of this WR are very diffcuilt to gather and actually we belive that it will be used against our side, we suggested another form for this WR but they refused it.
The question is can they request the issuance of this WR without issuance of a variation as this is an additional requirement to the contract in view of the FIDIC 99 as well as our specs.?
Regards,
Karim
Replies