Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Change Order VS Variation Order

8 replies [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Dear All,
I also wanted to know the difference between change order and variation order.
Regards
deb

Replies

ashraf alawady
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 26 Aug 2006
Posts: 320
Groups: None
No difference in terms of change order and variation order
Thanks
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Thanks Anoon and Ashraf i believe i got the point.
regards
deb
Ashraf Jahangeer
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Deb,

Anoon is right as there are also in some contracts like I have a term called "Adjustment Order".

So it all depends upon how the term is defined in your Contract.

Regards,

Ashraf
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
if it’s defined in your Contract, then that’s the definition, otherwise, forget it! i suppose Variations and Change Orders got the same intent
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
hello anoon , then tell me what si change order
regards
deb
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
then you work on Variations and Adjustments, forget Change Orders!
Pranab Kumar Deb
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
Hello Anoon,
My contract mentions "variation" -any change to the works , which is instructed or approved as a variation under clause 13( Variations and Adjustments ).
Change order is not mentioned
regards
deb
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
what does your Contract says?