Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Question

2 replies [Last post]
ram prasad
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 12 Apr 2007
Posts: 4
Groups: None
what is the difference between prime cost and provisional sum. which is benefical to the owner in a lumpsum construction contract.

Replies

Marcio Sampaio
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
A Prime Cost (PC’s) is an agreed, reasonable estimate for materials (fixtures and fittings) which you may not have selected at the time of entering into the contract. Usually, PC’s are one-off items, however they can relate to a large number of items when the labour cost remains constant. Examples may include kitchen and bathroom items.

A Provisional Sum (PS’s) is a reasonable estimate for material and labour of a particular part of the home which the builder cannot give a definite price for. The reason being the owner had not decided what the want at the time of entering into the contract. Examples are pool and landscaping.

Regards.
Bryan Russell
User offline. Last seen 10 years 38 weeks ago. Offline
Joined: 14 Dec 2005
Posts: 29
Groups: None
A Prime Cost or P.C. sum is an item in the BoQ used to define some form of special work for a service or article to be incorporated into the Works. It should have a secondary item for the tenderers to fill in for their work in taking delivery, offloading, fixing possibly, and overheads and profit as a percentage or a fixed sum.

A Provisional Sum is the a sum to be expended ONLY on the instructions of the Engineer for some task which was not defined at tender stage. Valuation will be done at applicable contract rates or new rates as in the Variation clause.

Definitions of Provisional Sums are in Sub-Clause 1 of FIDIC 99 and how to deal with them in S-C 13.5