Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Programme acceptance

5 replies [Last post]
Stuart Atkinson
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 16 Jan 2004
Posts: 68
Gents, any thoughts?

I am currently working on Option C of the ECC 2nd Edition. I just need a general feeling on the issue of acceptance of either the Clause 31 or 32 programmes.


Replies

Stuart Atkinson
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 16 Jan 2004
Posts: 68
I think you will agree Joseph, that It would have been more than helpful if a member of the Users group would have assisted. How long do they want the programming issues within their contract to remain ’woolley’ and ill-defined?
Stuart Atkinson
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks Joseph
Joseph Roberts
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 5 Feb 2003
Posts: 4
Groups: None
Stuart

Also working on a Option C contract

The PM is under a clear obligation to accept/reject the programme within a set time frame (Cl31.3). My understanding is that a failure to do so would lead to a dispute under 90.1 and the matter should be refered to adjudicator for resolution.

From past experienece I have often had programmes not replied to, however for political reasons there has not been the desire to take this to adudication. The situation of neither acceptance or rejection of the latest programme makes it difficult to operate the other clauses of the contract, in particular in relation to quoting for compensation events.
Stuart Atkinson
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks for your reply.
I am not particularly after specific areas; I just want planners thoughts on areas such as acceptance of the programme by the PM-is he required to accept, if not there appears to be no remedy.

Jihad Daniel
User offline. Last seen 8 years 34 weeks ago. Offline
Joined: 7 May 2005
Posts: 99
Groups: None
Dear Stuart,

Please be more specific and tell me your thoughts about these 2 clauses in order to share our ideas. It’s essential to differentiate between acceptance, consent, approval and agreement of programmes.

Regards,
J. Daniel