Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Premature Delivery of Material at Site

5 replies [Last post]
Razi Khan
User offline. Last seen 8 years 30 weeks ago. Offline
Joined: 17 Jun 2004
Posts: 74
Groups: None
Hi

What would be the most justified period for deciding delivery of certain material as "Premature" if it is not specified in the Contract of 2 years.

That is the differenc between Period of usage at site and delivery at site must not exceed ....... months.

How many months?

Cheers

Replies

Joshi Niraj
User offline. Last seen 19 years 46 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 27
Groups: None
PJ : I do not agree with your statement

"There is no such thing as pre-mature material or drawings on site, the sooner they are on site the better"

Premautre delivery also exists in construction contracts

PJ: if you do not have the knowledge about the things do not try to write and become expert of every thing OK .

Before giving opinion see the other aspects . OK.

Not become over smart in this forum . Try to understand the things.




Philip Jonker
User offline. Last seen 16 years 20 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
There is no such thing as pre-mature material or drawings on site, the sooner they are on site the better
Sukumaran Subaram...
User offline. Last seen 9 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
We need to view the premature material delivery from contractor’s point of view on project cashflow impact.

If the materials are delivered very early, contractor only can claim for materials on site. If the materials are idling for longer period contractor cannot claim for work progress until the physical work is started.

To maintain the materials quality, contractor need to arrange a store with proper maintenance. Again contractor need to fork out the cash to maintain the place and guard it with security personnel.

The feasible duration for premature delivery is suggested between 15 days to 30 days.

Any feedbacks are welcomed.

Regards.
Andrew Flowerdew
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Agree with Jaco, depends on the material

Ready Mixed Concrete - 2hrs could be premature if it may go out of spec if not poured within a certain time limit.

Pre cast concrete component - could be a week, could be 2 months depending on circumstances.
Jaco Stadler
User offline. Last seen 18 years 27 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
It depends on what the material is.

Assuming it has no shelf life and no warentee issues.I would suggest two months to Four before usage from a planning perspective. This give’s you more freedom to change the construction schedule if and when required. (And if the delivery is delayed this dont impact you that much)

I rather have material standing on site than having construction waiting for material.

If you have a space problem this then must be reduced.

Also keeping in mind what your internal target is