Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

acceleration of time extension

41 replies [Last post]
Emelyn Martinez
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 4 Oct 2003
Posts: 14
Groups: None
Hello Planet Planners!

I’m working on a Big Retail Mall Project. Our contract is design and build. We are the Project Manager, Designer & the Constructor. To date, the owner granted us a 3-month time extension - just in time for the mall opening. The thing is, the cut-off of our request for time extension was last February 2003. Another time extension claim will not be possible (as per owner) because the mall opening is already set and is no longer negotiable. With these, we can claim for acceleration cost. My question is, will it be possible if we establish first our probable time extension claim and it will be our baseline of our computation for acceleration cost?

Excess: We are a subsidiary company of the owner & our management prefer that instead of presenting claims, we have to focus on value engineering and other proposals to minimize the cost of the project and at the same time, achieving the requirements on time.

Replies

Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Mr. Jimmy,

I can clearly see that you have too many comments and Criticism to the ppl posting in that forum???
so why don’t u do all of us a big favour including to yourself and do not paticipate in that forum at all...

Actually, i wanted to post a different reply, but found out that it would be too rude for such a successful and useful forum, so i choose the one above


---------------
Jimmy robert
User offline. Last seen 19 years 13 weeks ago. Offline
Joined: 29 Sep 2004
Posts: 35
NESS

GOD bless you in your succeedings

Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Guys,
I appreciate your concerns as to whether or not I am providing an Exam Answering Service in this forum.
For a start, I only express my own opinions and every one of my views can be challenged and shown to be wrong. I certainly don’t have all the answers to all of your Claims related questions!!

In addition, I am also in correspondence with Hani outside of this forum - and a number of you will know that I am also in direct e-mail contact with you on a number of subjects outside of this forum, although our initial contact was through PP.

This forum is very much about networking with others, and to my mind it does succeed in that regard.

Cheers,

Stuart
Jimmy robert
User offline. Last seen 19 years 13 weeks ago. Offline
Joined: 29 Sep 2004
Posts: 35
ICQ:

Plz do not ask for moderator for deleting my threads

Its just my opinion and suggesstion.

You may also write . It is public forum not be made for you only. OK...

If u are in trouble u open your own forum.

It is not understandable that why the peopole not bear any critism only want praising praising and TC of others
IC Quiamco
User offline. Last seen 13 years 40 weeks ago. Offline
Joined: 19 Dec 2002
Posts: 48
Hmmm...also on this, Mr. Moderator what can you say about this?
Jimmy robert
User offline. Last seen 19 years 13 weeks ago. Offline
Joined: 29 Sep 2004
Posts: 35
Dear Hani

I think you need to be a course in UAE from a good Contract Management Consultant then come to this Forum so that you could be able to solved your problem yourself.

NESS : I think your threads are too long and time consuming with repitition the things but comprehensive to some extent so try to be short , It is not a Lecturer forum/room.

If you want to give detailed answer you should sent in detail on his PM or give the link for reference. Here plz be shorted.

Hope you will understand the situation


Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Dear Stuart,

Thank you very much for your comprehensive reply, definitely i will go through it and see where i do stand and get back to you.

Thanks again,

Hani
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Dear Hani,
I can fully sympathise with you since I also had a very similar situation a couple of years ago in Brazil, in which the Employer took back the site six weeks after the Contractor started work, the Contractor de-mobilised, the foundation works were substantially increased and then the Contractor restarted some 3 months later.

Without seeing the specifics of your Contract, I can only comment in general of course, but it is clear to me that you are entitled to a substantial amount of time with costs. Your position depends on whether your Contract Price is on a Lump Sum basis or is remeasurable – I assume that it is an EPC Contract on the basis of LSTK (Lump Sum Turn Key). In effect, what you have is a “Suspension of the Works” – though I doubt if the Client has admitted to calling it this in as many words!

Since only some 10% of the Contract Period elapsed before the Contractor had to demobilise, and since the work that he completed in that time (the excavation work) turned out to be completely abortive, I would argue that the Contractor had no opportunity to make any meaningful start to the execution of the Works in the first place. Consequently, I would argue that the 900 day Contract Period can only start after he has moved back on site – i.e., the clock for the full 900 days starts ticking on day 150. The Client will argue that there could have been some off-site work that could have been done, but this view is counter-argued by the fact that the Contractor could not plan or execute anything efficiently since he probably did not know when he could get back on site!

Because of the excessive disruption at the start of the project, and the changes to the foundations and the addition of an extra floor, (isn’t that a bit worrying – having a heavier building and lighter foundations??), I would also argue that the Contractor is entitled to reschedule the Works and submit a new Baseline Schedule to reflect these fundamental changes. (How many floors were there originally?) The start date of the new Baseline Schedule should be equal to day 150 and the new Schedule should reflect the additional work to the superstructure. Although there may be a reduction in the period for the new excavation work, this may well be nominal since a 10% reduction in foundation work does not necessarily lead to a 10% reduction in time required to carry out the foundations.

If the Client does not accept a new Baseline Schedule, but wants to stick to the original one, then you need to add into your schedule all of the delaying and disruptive events (including leads times!), such as the de- and re-mobilisations, the re-excavation work, the additional geotechnical work, the rework and recycle of your engineering of both the foundations and superstructure and obviously the period in which the Works were suspended from day 90 to day 150.

Re your question about the impact of the additional floor, this is in effect a Change/Variation Order and both the time and cost consequences of the extra floor must be reflected in your Contract Price and Contract Schedule. (I sincerely hope that you haven’t missed the deadline for the period of notice if there is one!). The fact that they are on or off the CP is not an issue. Don’t fall into the trap of thinking that because it is not on the CP (at the moment) that you can complete an extra floor within the original time frame!!

With regard to costs, again I would argue that the Contractor should be paid on a quantum meruit basis for the work already undertaken, including the time related overheads for the first 150 days, and that if it is a LS Contract Price, this should stand, but with increases to reflect inflation over the last 150 days on the new Baseline Schedule. The additional cost of the extra floor and any reduction in cost of the revised foundations (but remember that a reduction in the foundation work will also result in an increase in the cost of the re-engineering work for the new foundations!!) should be taken care of by the Contract’s Change/Variation Order mechanisms.
The Contractor must also be paid the cost of the de- and re-mobilisations. The “Suspension of Works” Clause in your Contract should set out the nature and extent of additional costs that the Contractor can claim.

Hani, I hope that I have thrown some light on your problems, but if you need any clarification, please feel free to contact me direct: stuart@rosmartin.com

Cheers,

Stuart

www.rosmartin.com
Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
i need all the assistance possible cause i am really in a strange situation.
I am working on a construction project, where the contract state a specific duration of 900 days. after site handing over and after alomost three months, all the site has been posessed again by the client for some soil improvements, during that time of soil improvement the Architect/Engineer modified the design of the foundation, those modifications have reduced the quantities of the foundations. Prior of client instruction to clear the site, the contractor ahs developped a baseline schedule and got it approved.....
When the Client took the sites from the contactor, the contractor had to demobilize some of his site offices and site hoardings.....
After almost two months the contractor regained posession of site......
Since the foundation was improved the client/owner has requested to increase the number of stories in some of the buildings.....

and here is a quick summary

-Contract Duration 900 days

-Instruction to clear site and demobilize day 90

-At that time Contractor established an approved baseline

- also contractor have performed geotechnical activities and finished excavtion.

-Soil Improvement ( out of contractor scope of work) finished after 60 days

-Contractor reposession of site day 150

- Site was backfilled, SO RE-EXCAVATION IS REQUIRED and new geotechnical investigation and testing are needed

-Scope of work for the contractor has been changed by adding extra floor to some buildings

-Foundation works have reduced in quantity due to value engineering done by the Architect/Engineer

Now here is the dilema

-when does the clock start ticking the 900 days? from day one or day 150?

-should we consider that the contractor have benefited from the first 150 days for technical submittals and some engineering and technical requirments. so we can start the clock after 150 days but not for 900 days anymore but for 840 days, instead????

- Do we see the actual construction duration in the baseline and grant him the same duration form his second reposession of the site??? Or Simply give him full 900 days from the second reposession since literaly no progress was made in his scope when the contractor gained reposession of the site????

-Do we implement the delays and the extra work performed by the client on the baseline schedule to see its impact, and then we add the slippage to the duartion and this would be the new finish date???

-How to acess the impact of the extra floor on the duration?? do we give the contractor and additional time for that extra floor, Even if the buildings which to receive the additional floor are not on the critical path of the approved baseline???

Please advise,
Thanks
Tauqeer Syed
User offline. Last seen 4 years 48 weeks ago. Offline
Joined: 22 Mar 2004
Posts: 17
I was working on a 300km twin pipelines project, it was a unique case in the sense that the project got approval for the extension of time as well as instructions to accelerate the schedule.

Due to some defaults by others, we got an extension of 9 months on the overall project’s commercial operation milestone. The project was twin pipelines system, the client instructed us to accelerate our activities on one line to complete it nearly 9 month before the revised overall project’s commercial operation milestone.

One pipeline was on extension of time and the other pipeline was on acceleration schedule.

We had to break our heads to launch this claim because direct & indirect cost were having postive and negative affects in both cases.

Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Dear Joe,
Thanks for the direction to the previous postings.
I do agree with you (and I think I said as much in my earlier post) that the Contract Programme is not a Contract Document unless it is specified as such in the Agreement.

I also agree with you that it is unfair to expect the Contractor to incur additional costs in overcoming delays for which he may not be responsible and then have to fight for them later; but if the world was fair, men would ride sidesaddle! ;-)

Cheers,
Stuart

www.rosmartin.com
Joe Mansour
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
(Correction)
Hi Stuart,
For the programme being a contract document or not, please refer to the following thread.
http://www.planningplanet.com/forum/forum_post.asp?Cat=7&Top=3128
particularly to David Bordoli’s last post.
I still beleive that the programme is not a contract document unless it is specifically stated so.

As to the case of granting the extension or not, if a Contractor follows your advice to accelerate and claim later, the Contractor will be incurring daily expenses and damages without knowing if he will ever get paid for them, except if he goes to court or arbitration, where he will incur additional costs. This totally unfair.
There should be a mechanism in the contract that forces the Engineer / Employer to releive the Contractor for costs incurred for reasons not due to him.

Joe
Joe Mansour
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
Hi Stuart,
For the programme being a contract document or not, please refer to the following thread.
http://www.planningplanet.com/forum/forum_post.asp?Cat=7&Top=3128
particularly to David Bordoli’s last post.
I still beleive that the programme is not a contract document unless it is specifically stated so.

As to the case of granting the extension or not, if a Contractor follows your advice to accelerate and claim later, the Contractor will be incurring daily expenses and damages without knowing if he will ever get paid for them, except if he goes to court or arbitration, where he will incur additional costs. This totally unfair.
There should be a mechanism in the contract that forces the Engineer / Employer to releif the Contractor or costs incurred for reasons not due to him.

Joe
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Hi Joe,

It is usual to find the Contract Documents identified in the Contract Agreement (which is separate to the Conditions of Contract; in fact, the FIDIC Conditions themselves will similarly be listed as one of the Contract Documents in the Contract Agreement, along with the Specification, Drawings and perhaps B/Qs.) Alternatively, the Contract Documents may be listed in the Appendix to Tender or form of Tender (see reference to Clause 43.1 of FIDIC Conditions)

In my experience, the Contract Programme (sometimes called the Master Schedule or Programme) is normally also identified and listed in the Contract Agreement as a Contract Document – if it is not listed, then someone (probably a lawyer!) has made a serious omission in drafting up the Contract!! The Documents listed in the Contract Agreement are prioritised under Clause 5.2 of the FIDIC Conditions, and therefore the Contract Programme should be identified and listed (in whatever priority!) under Clause 5.2.

Consequently, I suggest that if your Contract Programme is not identified and included in Clause 5.2 of FIDIC, then you may have a more difficult (but not impossible) struggle on your hands to get the Employer to give the Contract Programme its proper place and authority.

I have personal experience (in the Middle East and elsewhere) of an Engineer being very reluctant (or too lazy) to award an equitable EOT [bit like us Scotsmen opening our wallets…;-)]
You are correct that under FIDIC there is no set time limit upon the Engineer to make his determination, although there is a limit on the Contractor (28 days) by which to give notice and again to give details of his claim (see Clause 44.2). However, the Engineer is required to make such a decision “…having regard to all circumstances.” (see Clause 2.6), and I have argued in the past that the failure of the Engineer to make his EOT determination within a reasonable time is a breach of his duty under Clause 2.6, particularly if this causes hardship (such as additional costs and/or lost time) on the Contractor.

In your case, where the Engineer is too lazy (or scared!!) to properly grant an EOT, I would make him part of the formal problem, and you should give notice under Clause 44.1(e) that his failure to award the EOT is likely to affect the Contractor’s rights (to time and money) as noted in Clause 2.6(d). This brings the inaction/failures of the Engineer into the open and this alone can get things moving, since his inaction/failures may well hurt the Contractor and increase the Contractor’s entitlement to more time and money. (and ultimately the Employer will have to pay extra for his Engineer’s recalcitrance!)

This may all lead into a claim for Constructive Acceleration; my advice (especially if you are likely to incur LADs if you don’t accelerate), would be to accelerate as ordered, but continuously keep giving notice under Clause 44 and submit your reasons and costs (see Clause 44.2) at intervals well with in the 28 day limit (probably weekly if you can!).

I am well ware of the pressure exerted by Employers in this regard, but would suggest that pressure from the Contractor’s side can also be made in terms of ensuring that you present your claim under the Contract for time and money on a virtually continuous basis – just don’t miss any of the notice deadlines!!

Hope this helps,

Cheers,
Stuart

www.rosmartin.com
Joe Mansour
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
Dear Stuart,
Thanks for your elaborate reply.
Let me note first that under FIDIC, the programme of works is not a Contract Document. The "Time for Completion" as stated in the Contract, or as extended under Clause 44 is the only reference to time in the regular FIDIC.

I would like to quote from Corbett’s legal guide to FIDIC:
"there is no power given to the Engineer under the Contract to order acceleration at the Employer’s expense.
and "It is therefore necessary for a Contractor to demonstrate a variation of the contract as distinct from a variation to pursuant to the contract. He must show that the Employer and the Contractor have agreed that the Contractor should accelerate and that the Employer would pay him so to do".

However, the problem arises, and it is a very common one, when the Engineer is reluctant to determine an extension since he has no time limit to do it, and he orders acceleration. The delay is not acknowledged yet by the Engineer to be a non-Contractor’s delay. In that case, what would the Contractor do: accelerate and claim for costs later, or refuse to accelerate until an agreement is reached?
Let me tell that in the middle east, extension of time is very very difficult to obtain, due to the enormous pressure made by Employers.

Interested to know your views and experience.

Joe
Shahzad Munawar
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Good interpretation of Clauses with respect to compensation of EOT for a Conntractor - very helpful in some other cases also
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Dear Joe,

Under Clause 2.5 of FIDIC (Red Book), the Engineer – on behalf of the Employer – is allowed to issue instructions in writing to the Contractor, (and if given orally, to be confirmed in writing by the Contractor) and
“…the Contractor shall comply with such instruction.”

This assumes that the Engineer is entitled to issue said instructions under his authority to do so as set out in Clause 2.1; in the case of issuing instructions related to acceleration it would be reasonable to assume that the Engineer would have this authority.

Under Clause 46.1, where the Contractor is not maintaining adequate progress to achieve timely completion and where there is no excusable delay, then the Engineer (again on behalf of the Employer) is required to tell the Contractor that he is in delay, and the Contractor is then required to
“…take such steps as are necessary…to expedite progress so as to comply with the Time for Completion.” [i.e. accelerate !!]

In such circumstances, the Contractor is not entitled to any extra payment, since this relates to a situation for which the Contractor is responsible for the delay (non-excusable delay).

Is your predicament, however, related to a situation in which there is no delay (at least not one caused by the Contractor) and the Employer simply wants to have his project completed earlier?
If this is the case, I can see no provisions in the FIDIC Conditions that allow the Employer to instruct the Contractor to accelerate “just for the hell of it!” Of course, this does not prevent the parties from reaching mutual agreement on Acceleration Programmes on the basis that the Contractor will accelerate, provided that he is paid his extra costs – such agreements take place all the time, one way or another!

But under FIDIC, I would suggest that the Employer has no right to instruct the Contractor to accelerate without agreed compensation. Note that Clause 41.1 of FIDIC requires the Contractor to start the Works as soon as possible after notice to commence, and that the Contractor
“…shall proceed with the Works with the due expedition and without delay.” [in other words – in accordance with the agreed Contract Programme!!]

In addition, under Clause 8.1 of FIDIC, the Contractor is obliged
“…with due care and diligence, …(to the extent provided by the Contract), execute and complete the Works…in accordance with the Contract.”
This also means that the Contractor is required to carry out the project in accordance with the agreed Contract Programme (assuming that it is formally part of the Contract Documents), and as such, neither party can unilaterally change a Contract Document. So in this way, the Employer is actually prevented from and not allowed to instruct the Contractor to accelerate, since the Contractor, under Clause 8.1, is only required to carry out the Works in accordance with the Contract Documents, i.e., including being in accordance with the agreed Contract Programme.

I hope that this helps a bit. If it is unclear of if you need any further clarification, please feel free to contact me direct: stuart@rosmartin.com

Cheers,
Stuart

www.rosmartin.com
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear Stuart,

Let me rephrase the question:
Is the Contractor under an obligation to accelerate if the Employer instructs him to do so?

If you are familiar with the FIDIC red book, I would like to know specifically if under this form of contract, the Employer has the right to instruct acceleration, and under which clause.

Thanks

Joe Mansour
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Dear Guest,
regarding the question about the Client’s right to force acceleration, the answer (as usual!) lies in te detail of the specific Contract!
I have seen Contracts where the Client is specifically allowed to instruct acceleration where he feels that the Contractor is in delay.
In addition, I would also suggest that the Client often has an implied entitlement under the Contract - even if it is not specifically identified as such - to instruct the Contractor to accelerate. This implied right could be viewed as being the Client’s right to protect his project investment, though such an implied right would less in the case of an LSTK Contract, where the Contractor has full responsibility.

I am not sure that a Contract Addendum would be the correct vehicle to impose acceleration.

In the final analysis, however, the real issue is not who instructs the acceleration, but the cause of the need to accelerate and who is going to pay for it!

Hope this helps,
Cheers,
Stuart

www.rosmartin.com
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Dear Hani,
I was involved in a project in the USA where the Contractor claimed 5 months EOT, but the Client granted only an EOT of 2 months. This still left a "shortfall" of 3 months, and in order to avoid LAD’s etc., the Contractor had to implement constructive acceleration measures, even though an EOT had been granted.

Such situations are not entirely unusual, though I agree that in certain parts of the world Clients/Owners are very reluctant to grant any amount of EOT, even when the Contractor has a clear entitlement under the Contract!!

Cheers,
Stuart
www.rosmartin.com
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hi Guys,

One important question is to be asked:

Has the Client the right at all to order acceleration under the Contract?

Some say yes, others say no but it has to be agreed on under an addendum to the Contract.

What would you say?
Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Stuart,

theoratically, you are 100% right. But pratically, this is not a regular thing to happen, i did not know or hear that the client has granted a contractor EOT and after that an acceleration of time cause the EOT is not sufficient.....

I do not think there such understanding client anymore..


Hani
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Stuart,

I agree but still you have to evaluate the difference between the EOT granted and EOT requested to claim for constructive acceleration.

proj_planner
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
proj_planner,
To answer the question in your opening line, it is possible for a Contractor to be granted an EOT, but for it to be insufficient or incorrect; i.e., the Contractor is really entitled to a period longer than that given in the EOT.
In such a case, the Contractor could well be faced with having to engage in constructive acceleration measures, even though an EOT was granted.

Stuart
www.rosmartin.com
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
The point is if you are granted an EOT, what acceleration can you claim for? Whereas if you are denied the EOT for an excusable delay, acceleration is the only way to complete the project on last agreed completion date, which the Client insist to respect.

A contractor’s claim for constructive acceleration should meet the following criteria:

The delay is a result of causes that would entitle the contractor to time extension under the contract

The contractor requests time extension for the delay in a timely manner, in accordance with the contract

The owner fails or refuses to grant a time extension to the contractor

The owner requires the contractor to complete the work in accordance with the original schedule or indicates an intention to penalize the contractor for failing to complete the work in accordance with the original contract schedule

The contractor then endeavors to accelerate by working additional hours, by committing additional resources, or by other means

The contractor incurs additional expense in carrying out these acceleration efforts

Cheers,

proj_planner
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
I think you will find that for a claim for constructive acceleration to be valid, the Contractor is required to claim for an EOT and for that request to be either denied or issued too late to be effective!

Emelyn - you posted some time ago that your revised completion date was 15 August, which was last week. I am curious to know if you completed in time, or did you have further delays that prevented you from completing?

Stuart
www.rosmartin.com
Brennan Westworth
User offline. Last seen 7 years 29 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
As you are a subsidiary company it would probably be better to go straight for the acceleration claim since you know the completion date is fixed. As part of your claim for acceleration you would need to show that the delay is valid using standard EOT principals.

This would be seen as a proactive move and probably viewed more favorably by the client as it would save him the stress of thinking he isnt going to get his mall open in time.
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Ms. Martinez,

I think it is best to submit a request for an extension of time first and when it is denied follow it up with a constructive acceleration claim based the EOT claim. In case the EOT is granted, you can still claim for disruption or prolongation (whichever is applicable).

proj_planner
Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Hi Emelyn,

I think that you will need first to establish EOT and have it granted by the Client then you can proceed for an acceleration of time claim, but i think that EOT will not be an easy one as it may seem. It will require a lot of preparation and arguments. All the relevant points must a very clear impact on the revised baseline, which should strengthen your claim and request.

Good Luck,

Hani
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Emelyn,

I sent you two e-mails yesterday to your yahoo e-mail address. Did you receive them OK?

Cheers
Stuart
www.rosmartin.com
Emelyn Martinez
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 4 Oct 2003
Posts: 14
Groups: None
Hi Hani.

The following were the first grounds for time extension:
1) Late issuance of building permit.
2) Proposed changing of the construction sequence due to some marketing plans whereas some areas were put on-hold for quite some time.
3) Unworkable weather conditions.

For this time, my grounds shall be:
1)Design changes.
2)Disruption due to marketing requirements.
3)Additional requirements which are deemed not included in the original contract.
4) Unworkable weather conditions.

We are on a GMP (Guaranteed Maximum Price) Contract. We are handling the design, management and construction. And again, my company is 100% subsidized by the owner.

Thanks.


To Stuart,

Thanks for the ideas. It will help me a lot. I’ll try to grab a copy of the book.


Best regards,

YEN
Hani El Sherbini
User offline. Last seen 17 years 39 weeks ago. Offline
Joined: 7 Mar 2004
Posts: 18
Groups: None
Hi Emelyn,

Can you please tell us what were your reson or exuses for the first EOT and what are those of the second that you are trying to establish at the moment

Hani
Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Hi Emelyn,
Constructive Acceleration is defined by the US Corps of Engineers as
"An act or failure to act by [Employer] which does not recognise the Contractor has encountered excusable delay for which he is entitled to (an EOT) and which required Contractor to accelerate his programme in order to complete the contract requirements by the existing contract completion date. This situation may be brought about by [Employer’s] denial of a valid request for a contract time extension or by [Employer’s]untimely granting of a time extension."

The best reference that I have found on Constructive Acceleration is in Keith Pickavance’s book "Delay and Disruption in Construction Contracts".

I have been successfull in running this argument on a few occasions, but it is easier to win the argument if you have a contract that is more American based, since there is a bit of Americam case law that supports this idea. It is only catching up very slowly in Europe...but if you have a good convincing case, then the logic is faultless.
Hope this helps,
Stuart
www.rosmartin.com
Emelyn Martinez
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 4 Oct 2003
Posts: 14
Groups: None
Thanks, Stuart.

Constructive accelaration is somewhat new to me. Would you mind if you elaborate the subject further?

Stuart Ness
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Emelyn,
It sounds to me as if you may have an entitlement to Constructive Acceleration. This happens when the Contractor is caught between a rock and a hard place! (nothing new there!!)
If you have an excusable delay, are entitled to an EOT but it has been either denied to you or given to you too late, and if your only recourse is to accelerate in order to meet the due completion date, then you may have a case of Constructive Acceleration. This is a concept now being accepted by arbitrations and courts in a number of locations.
Cheers,
Stuart
Emelyn Martinez
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 4 Oct 2003
Posts: 14
Groups: None
Thanks for the replies.

As of to-date progress, completion date of 15 Aug 2004 is still attainable. The mall opening is deemed important to the marketing & cash flow of the owner. I just want an entitlement of acceleration cost, considering the 2nd request for time extension. Our contract is design and built and all design, management & operation issues always fall back on us. Also, our company is under the umbrella of the owner, being a subsidiary, and at times, the traditional procedures are not followed. We got a very good working relationship but I guess, there must exist a win-win relationship.

Luca Basile
User offline. Last seen 9 years 41 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Which kind of contract it is? (BOQ, reimbursable, etc ...)
Which main rules are applicable? What is defined in the special condition?

Your baseline was in line with the 15May04 completion date?

The opening data is something I understood not easily negotiable as they already set up all, and could be an image problem.
Opening a shopping centre on a certain time is a marketing problem also.

How are the relationships with the Client?
May be a more flexibility and not traditional approach must should be adopted.
If You can not real meet the actual completion try to propose, to the Client, at the same time the two schedules.
One with the more time required (Nov 04) and the recovery plan (Aug 04) together with the cost implication to meet this completion date.
At the end the Client will make his cost/benefits analysis and determine what ever is better for him, to pay the acceleration or allow You more time.
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I am a bit confused with all your dates, basically, if the opening is on a certain date, and you prove time entitlement beyond it, then to be able to achieve the opening date, you need say, extra resources, overtime etc. All these, you need to substantiate and prove.
I am sure most of us have come across something like this, again, at critical stage towards the opening, keep ALL records properly.
Good Luck

Abdullah Haji Hukum
Forum Guest
User offline. Last seen 17 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
You need to establish your entitlement to time extension, then, you argue on the difference between time granted and your entitlement, and also, when you actually complete the works. From here only the acceleration can be established.
Again, the Client usually does not recognise this, unless you can substantiate it convincingly.

Abdullah Haji Hukum
Emelyn Martinez
User offline. Last seen 12 years 33 weeks ago. Offline
Joined: 4 Oct 2003
Posts: 14
Groups: None
Thanks, Shahzad.

Obviously, the time extension must be first established and granted by the owner. My question is that the owner will not allow for another time extension because the mall (our current project) opening is already non-negotiable. The situation is like this:
Orig Contract Duration : 16 Jul 2002-15 May 2004
1st Time Extension Claim: 3 months (granted)
Period of Claim for Time Extnsn: 16 Jul 2002 - 28 Feb 2003
Revised Contract Duration : 16 Jul 2002 - 15 Aug 2004
2nd Time Extension Claim: 3 months
Period of Claim for Time Extsn: 1 Mar 2003 - 15 May 2004
Project Turn-over: 16 Aug 2004
If the second claim will be granted, the project completion will be on 15 Nov 2004 and we barely have 2 months left to complete the project in time for the mall opening. How can we claim for acceleration in this scenario?


Shahzad Munawar
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
First you will have to establish Extension of Time and if this Extension is granted/approved then you will be entiteld for the acceleration claim accordingly.