Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Assessing Delays in Agile & Distributed Projects

No replies
Patrick Weaver
User offline. Last seen 5 days 5 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

Published in the April edition of PM World Journal,  our latest paper, Assessing Delays in Agile & Distributed Projectslooks at the challenge of assessing delay and disruption in projects where a CPM schedule is not being used:  https://pmworldjournal.com/

For the last 50 or more years, the internationally recognized approaches to assessing delay and disruption has been based on the forensic assessment of a CPM schedule. However, the methods detailed in RP 29R-03 Forensic Schedule Analysis and the SCL Delay and Disruption Protocol do not offer a viable option for assessing delay and disruption in a wide range of projects including:
- Projects managed using an agile or iterative approach to development.
- Distributed projects where there is no particular requirement for large parts of the work to be completed in any particular order.
- Projects managed using Lean Construction and similar approaches where the forward planning is iterative and short term.

But, the law of contract will not change. If the contractor fails to comply with the contract requirements to deliver the defined scope, within the required time the contractor will be in breach of contact and liable to pay damages to the client for that breach.  One way to minimize the contractor’s exposure to damages, is to claim extensions of time to the contract for delay events, particularly delays caused by the client.  What has been missing in the literature to this point in time is a set of processes for calculating the delay in the absence of a viable CPM schedule. The good news is the law was quite capable of sorting out these questions before CPM was invented, what’s missing in the current situation is an approach that can be used to prove a delay in agile or distributed projects.

This paper defines a set of delay assessment methods that will provide a robust and defensible assessment of delay in projects where there simply is no viable CPM schedule. The effect of any intervening event is considered in terms of the delay and disruption caused by the loss of resource efficiency, rather than its effect on a predetermined, arbitrary, sequence of activities.

Download Assessing Delays in Agile & Distributed Projects and supporting materials from: https://mosaicprojects.com.au/PMKI-ITC-020.php#ADD