Hi,
I have a programme where I have been recording progress on a weekly basis but I have not been using it as a live programme i.e one that you reschedule on a weekly basis. I am now trying to crate an as built programme from it.
I know that If I do a reschedule at the last progress period only those activities not complete will shift and complete tasks dont shift from the baseline however I am wanting to show the progress throughout the project.
Does anyone know how to do tihs?
I was thinking I would have to go back to the first progress period and reschedule to that then the 2nd , 3rd 4th etc so activities shfted to period in wihch they were complete but not sure but this seems like a lot of work and not sure how to set reschedule options to only account for the progress at that week in the reschedule.
Any help appreciated.
Regards
Chris
Replies