Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

'Is a project' function in Asta

1 reply [Last post]
Seethal Sajan
User offline. Last seen 5 years 46 weeks ago. Offline
Joined: 15 Dec 2012
Posts: 2
Groups: None

Hi

Has anyone used the 'is a project' function in Asta?

Please explain what it is.

Does Asta allow to have a master programme and sub-programmes linked to it so that changes made to master will be reflected on the sub ones?

Thanks

Susan

Replies

Ben Taunt
User offline. Last seen 1 year 11 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Susan,

You can structure your file in Powerproject such that you can have various levels of data.  For example, you might group tasks together using the "Summarise" feature to show them under a Summary Bar.  You might then Summarise a number of Summary Bars together to represent a phase of the project.  You could then Summarise these phases again to show a Project level.  You could then group these projects together to represent a Programme.  And finally, group programmes into different Portfolios...

Links can be created between any parts of these activities.

"Is a Project" is simply a flag that is assigned to a Summary or Expanded Task to indicate it's significance.  It is more widely used in the Enterprise version of the software than in the standalone client, but the feature does the same in both versions.  It can be very useful when exporting Powerproject data out into reporting systems, using our BI tools (Business Intelligence data for driving dashboards etc).

You can read much more about this in the Help Files such as here: http://help.elecosoft.com/powerproject/english/14.0.04/#HTML_Topics/Conceptual/Structuring_your_project/Structuring_your_project.htm

Thanks,

Ben @ Powerproject