Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Changing end date on progressed activity

3 replies [Last post]
Harry Angell
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 13 Oct 2014
Posts: 17
Groups: None

I've just started using Asta PP after working on P6, and I'm a bit thrown by how you accomplish even simple things.

In P6 once I had marked the progress on an activity you could use the Anticipated end date to change the planned end date of a task, now this may be a dense question, but how do I do the equivilent in Asta?

If I try and change the finish date, it simply jumps back to the original finish, it won't accept the new date I'm giving it.

Thanks

 

h-angell

Replies

Mike Testro
User offline. Last seen 36 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Yes. But the point about rules is knowing when it is safe to break them.

Andrew Pearce
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175

Mike dosnt that violate your planning rules on constraints and ALAP?

Mike Testro
User offline. Last seen 36 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Harry

Asta is a completely different system from P6 so it will take a little time to adjust but the effort will be well rewarded.

For one thing Asta will not accept negative float and the stated end date is advisory only.

In this way you cannot distort the logic - it is what it is.

You can change the finish date by moving the last milestone and flagging it to finish "On or After" then by setting the tasks ALAP they will move to the later date and turn critical.

You can also set the two dates - Earliest v Latest in the date columns.

Keep at it and use PP whenever you need us.

Best regards

Mike T.