Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Milestone

1 reply [Last post]
anu h
User offline. Last seen 6 years 3 days ago. Offline
Joined: 22 Oct 2016
Posts: 6
Groups: None

I downloaded free trial of latest ASTA version. ried to type a new programme, However, when I tried to create a milestone with '0' on duration column it wont allow me to do that. Normally on a milestone start date and finish time is same. But in my programme there is one day difference between start and finish time. It wont allow me to change it into same date on both columns. How do I create milestone? It seems some sort of setting but I cant figure it out ant help will be greately appreciated

Replies

Mike Testro
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anu - Welcome to planning planet.

There are a number of ways to create a milesstone.

1. Type "0d" days in the duration field.

2. Right click the task and select Options > Change Into > Milestone

3. Hold the end of the task and drag sharp left to turn it into a milestone.

I hope that helps.

Best regards

Mike Testro