Historgram

2 replies [Last post]
Andy Hudson
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

what os the easiest way to prepare histogram in asta?

thanks

Replies

Andy Hudson
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 18 Oct 2016
Posts: 33
Groups: None

Thanks Mike

Mike Testro
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Andy - welcome to planning planet.

There are two ways.

1. Use the histogram software built into the system - this is best if you want to demonstrate a histogram under a project view. Look in the Help section for full instructions.

2. Export the histogram data to excell and use that to generate the graphs - this gives you better flexibility and presentation options.

Best regards

Mike Testro