Hello,
I'm currently having an issue with Asta which I'm struggling to resolve due to the lack of many other people in my company that use this software at present. Let me try and paint as clear a picture as possible:
I have a progress report which I am recording weekly against Baseline Rev 1 in the view named "Progress".
In my view named "Bar Chart" the progress entry/bar splitting etc is showing, so I decided not to revise up to Rev 2 here as I require my newly revised baseline to be Baseline Rev 1 + Revised Dates + a few additional tasks.
I thought that the bar should remain untouched in the view named "Bar Chart" which would make life so much easier. (I am working to project template made by the senior planner that has since departed the company).
What I have done is taken my initial programme (the result of which is Baseline Rev 1 for progress) and revised dates accordingly as well as added these additional tasks and named the result of this Baseline Rev 2.
When I import Baseline Rev 2 into my progress report, the planned dates are updated as expected BUT the new tasks are not there.
Can anyone help me with this issue?
Regards,
SM
Replies