Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Negative Values For Task Allocations (Cost / Income)

2 replies [Last post]
Chris Lothian
User offline. Last seen 1 year 18 weeks ago. Offline
Joined: 18 May 2007
Posts: 34

Hi All,

 

Does anyone know if it's possible to have a negative value against a income / cost?

 

Reason for wanting to do this, is that I have an a highway maintenance contract where the client has given us anticipated spends against a list of tasks, but the actual spend was less. Rather than go through and adjust all the anticiapted spends, I was hoping to insert a new task with a negative value against it which represented the sum of the underspend.

 

Kind Regards,

 

Chris

 

Replies

Ben Taunt
User offline. Last seen 51 weeks 5 days ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Chris,

Whilst I agree with Craig's suggestion, for reference you can't have a negative cost.  If you try entering one, Asta Powerproject will chuck up a warning stating the value must be greater than zero.  That is the point of the alternative income field within Asta - other software which has no concept of income does allow you to have a negative cost but only to get around that deficency.

So I guess you could use the income field to record the underspend...?  As the net amount would therefore be orginial cost less the underspend...?  Sounds messy though.

Cheers,

Ben @ Asta

Craig Adams
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 32

Hi Chris,

Wouldn't you just enter actual cost so you could use Asta cost functions?

Kind regards,

Craig