Network Diagrams

3 replies [Last post]
Craig Adams
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 32

Fellow Astarians,

How does one produce a Network diagram in Asta, can someone please enlighten me.

Knid regards,

Craig Adams

Replies

Craig Adams
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 32

OOOO, that's a bit embarrasing!

Cheers,

Craig Adams

Chris Rymer
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None

Hi Craig

We did have a free add on product called Powernet that we have recently had to withdraw from the knowledgebase. This is due to a Microsoft update making the product unusable at the moment.

We are planning on writing a new product in 2013, so keep an eye on the website for release dates

Regards

 

Chris

Mike Testro
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

As far as I can see in v12 it can't be done.

I seem to recall an earlier version - pre v5 - that had such a facility.

You can save it as an .xer file and open up in P6 and print off a network from there.

I will now go and wash my mouth out with soap.

Best regards

Mike Testro