Powerproject and Lean/Last Planner System

2 replies [Last post]
Justin Nutt
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 8 Jul 2011
Posts: 4
Groups: None

Hello All,

Does anyone have experience or knowledge on how Asta Powerproject lends iteself to Lean Construction and Last Planner System?  Is anyone using the line of balance feature?

Justin

Replies

Justin Nutt
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 8 Jul 2011
Posts: 4
Groups: None

Thanks Mike and thank you for the reply. 

As far as my first questio, I was looking to see if anyone is using features, such as Line of Balance, to do things like track and view planned versus actual productivity rates, and then use those projections to take necessary actions.  I would think these type of features would lend themselves very well to the Last Planner System and Lean.

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Justin

Welcome to Planning Planet.

I do not undersatnd your first question.

Lean Planning describes a brainstorming session - usually involving post-it notes and red string.

The results can then be transferred to any software.

The Line of Balance - Time Chain add on to v 12 is most welcome - but you have to set things up in task per line mode first.

I last used it on a 500km oil pipe line up the west coast of India and it was very effective.

Best regards

Mike Testro