Site progress

5 replies [Last post]
Dave Crosby
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 8 Oct 2008
Posts: 79
Is anyone on here using Site Porgress? This allows you to update progress in Powerproject via the web. I would be interested in hearing feedback from anyone who is or has used it.

Replies

Ian Watts
User offline. Last seen 14 years 48 weeks ago. Offline
Joined: 16 Dec 2008
Posts: 4
Groups: None
Hi Mike,
Appreciate the help, can you give me more detail.

Kind regards

Ian Watts
Mike Testro
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Ian

Are you using task per line mode?

Have you tried setting the reschedule to Link Around Completed tasks?

Best regards

Mike Testro
Ian Watts
User offline. Last seen 14 years 48 weeks ago. Offline
Joined: 16 Dec 2008
Posts: 4
Groups: None
Hi Dave

I use it on three projects and have had great success,saves me a lot of time, the only promlem is site managers progress before the previous task is complete, making the drop line unsure of where to go
Dave Crosby
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 8 Oct 2008
Posts: 79
Thanks Mike.
I hope you weren’t discouraged by an early prototype. No doubt it has come a long way since then. Remote access to the web is so much better than it used to be as well.

Cheers,

Dave.
Mike Testro
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Dave

I have never used it although I did buy an early prototype that worked with Task Per Line mode but not very succesfully.

I do remote progress updates from sites by email.

The site fills in a spreadsheet with the activities and the percentage column and email it to me and I just cut and paste into the programme.

Best regards

Mike Testro