Checking the Calendar against tasks

3 replies [Last post]
Laurie Willis
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Hi,

If you have multiple calendars, how can you check which calendar you have previously assigned to a task without adjusting the task length.

Thanks, Laurie

Replies

Jamie Robson
User offline. Last seen 5 years 42 weeks ago. Offline
Joined: 8 Apr 2002
Posts: 3
Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
Good luck!
Jamie
Laurie Willis
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Got it. Thanks Alexandre.