Senior Planner engineer, Balfour Beatty Major Projects, 1.M25 Motorway Widening J16 to J23

START Date: 
February, 2009

Current Role

The Highways Agency is widening approximately 102 kl of M25 by adding a lane in each direction to make generally a 4 –lane Motorway. The widening undertaken between J16 (M40) to 23 (A1(M)), by Skanska Balfour Beatty Joint venture.

 M25 J16 to 18

 

  • Prepare submission programme for Highways agency, followed by detailed construction programme to include resources, cost and quantities of individual activity.
  • Prepare KPI’s for major works to include Concrete, Drainage, Excavation & Fill maters, Drainage, etc. and draw histogram for individuals, update and report weekly progress.