Senior Planner, Group five, Civil (roads and bridges)
START Date:
August, 2008
END Date:
October, 2010 Create Baseline Schedule in CCS Candy.
Develop package measurement tools.
Measure Progress.
Hi-light scope change and impact.
Manage Continuous Improvement.
Report on both Client and Director levels.
Experience Hours (Planning & Scheduling):
4500 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: